Software Updates : Power Projects
Jul 05: 8Project Name: Pumped Storage Hydro Power Greenfield Project
8Project Cost: 7000 crores
8Project Description: Owner has been granted environment clearance for a 1500 MW Pumped Storage Plant. Package wise bids are expected.
8Project Event: RFQs for civil and H&M works are expected by August 2018.
8Expenditure Approval: Q4:2018
8RFQ Date: Aug/2018
8Release Date: Aug/2018
8Start Date: Q2:2019   
8Completion Date: Q3:2024
Click here for more information

8Project Name: Thermal Power Station Maintenance Project 
8Project Cost: 15 crores
8Project Description: Promoter's bids for a 45-day scheduled annual overhaul in 3000 MW thermal power plant is getting delayed due to lack of preparation of Notice Inviting Tender document. The mandatory job includes refurbishment of pressure parts of boiler, replacement of turbine rotating blades, burner refurbishment, replacement of air preheater (APH) basket, replacement of radial, axial and rotor post seals of air preheater, sector plates in air preheater which gets corroded during operation, among others.
8Project Event: RFQs for required equipment for the overhaul are expected by the end of July 2018.
Click here for more information

8Project Name: Thermal Power Station - Dismantling
8Project Cost: 83 crores
8Project Description: The owner is planning to retire and dismantle all the plants of 340 MW coal based thermal power station as it has aged more than 25 years. Further bids are expected soon.
8Project Event: RFQ for dismantling services of various equipment is expected by October 2018.
8Expenditure Approval: 2018
8RFQ Date: Oct/2018
8Release Date: Oct/2018
8Start Date: Q2:2019
8Completion Date: Q3:2020
Click here for more information

**********************************