Rs 3500 crore greenfield LNG project: More RFQs in August
Jun 28: 8Project Name: Another Greenfield LPG Pipeline Project
8Project Cost: Rs 3500 crore
8Project Description: Owner has hired the PMC contractor
8Project Event: RFQ for the 150 Km mainline pipe is expected August 2018. RFQ for the laying work for the first 100 Km is expected by September 2018.
8Expenditure Approval: Q2:2016
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q1:2017
8Completion Date: Dec/2020