Software updates: Fertilizer projects
Jun 20: Ammonia-Urea & Captive Power Plant Greenfield Project        
8Cost - Rs  10741 Crore
8Project Event: RFQ for LSTK contractor was floated in May 2017 for Generating Ammonia Syn. Gas & Carbon Dioxide Gas and the last date for bids have been extended from 18 June to 28 June 2018. The due date for submission of bids for the ammonia-urea plant is extended from 21 May to 16 July 2018.
Click here for more information  
Single/Triple Super Phosphate Greenfield Project  
8Cost - Rs 30 Crore
8Project Event: The selection process for anf EPC contractor is ongoing.
Click here for more information
Phosphoric Acid Greenfield Project            
8Cost - Rs 10 Crore
8Project Event: The proposal for the environmental clearance was submitted this month, Public hearing is likely in July. They are looking for a local EPC contractor and contract likely to be finalized in August 2018
Click here for more information


**********************************