Jun 19: 8Project Name: Refinery Greenfield Propylene Derivative Petrochemical Project
8Project Cost: Rs 5000 crore
8Project Description: The owner along with the EPC contractor and licensor are carrying out engineering activities to install a Propylene Derivatives Petrochemical complex. Equipment ordering is nearly completed. Moreover out of 877 types of equipment 300 types of equipment received. civil and structural for all 3 units, off-sites and building jobs are in the advanced stage as well as Mechanical work for all 3 units and cooling tower jobs are in progress The commissioning date has been rescheduled for May 2019 prior to August 2018. Further RFQs are coming soon.
8Project Event: RFQ for the instrumentation work for Oxo-alcohols is expected by August 2018.
RFQ for the Instrumentation works for Acrylic acid, Acrylates and offsite is expected by last week of June 2018.
8Expenditure Approval: Q2:2015
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2015
8Completion Date: May/2019