Jun 13: 8Project Name: Hydroelectric Power Greenfield Project 8Project Cost: 4500 crores 8Project Description: Owner will come out with a bid for 400 MW Greenfield hydroelectric Power project of consultancy services for catchment area treatment (CAT) plan soon. 8Project Event: RFQs for consultancy services for catchment area treatment (CAT) plan are expected by Q3 2018. 8Expenditure Approval: 2017 8RFQ Date: Q3:2018 8Release Date: Q3:2018 8Start Date: Q2:2020 8Completion Date: Q3:2025 Click here for more information 8Project Name: Thermal Power Station - Dismantling Project 8Project Cost: 100 crores 8Project Description: Promoter is planning to retire and dismantle the Units in the 500 MW thermal power station. Further RFQs are expected soon. 8Project Event:RFQs for dismantling services are expected by the Q1 2019. 8Expenditure Approval: Q3:2018 8RFQ Date: Q1:2019 8Release Date: Q1:2019 8Start Date: Q3:2019 8Completion Date: Q1:2020 Click here for more information