Jun 12: 8Project Name: Combined Cycle Power Plant - Maintenance Contractor Project 8Project Cost: 6 crores 8Project Description: Owner is planning to come out with a bid for electrical maintenance contract of the 400 MW combined cycle gas power plant. 8Project Event: RFQs for biennial electrical maintenance contract are expected by the end of June 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: 25/Jun/2018 8Release Date: 28/Jun/2018 8Start Date: Q4:2018 8Completion Date: Q4:2020 Click here for more information 8Project Name: Hydro Power Station Maintenance Project 8Project Cost: 4 crores 8Project Description: Owner has planned a 25-day scheduled maintenance in the 500 MW Hydroelectric Station covering annual inspection and overhaul of equipment which includes overhauling and checking of auxiliary parts of the turbine-generator set, bearing sets, sensors and seals. The mandatory job includes replacement of the turbine bearings, gland seals, change of worn out bushes of guide vanes journals, among others. 8Project Event:RFQs for required equipment are expected by the October 2018. Click here for more information 8Project Name: Thermal Power Station - FGD Addition 8Project Cost: 825 crores 8Project Description: The owner's plan to install flue gas desulphurization (FGD) unit in the 2400 MW thermal power station has been delayed due to financial crunch. Further bids are expected soon. 8Project Event:RFQ for consultancy services for the site survey and preparation of the feasibility report is expected by Q4 2018. 8Expenditure Approval: Q2:2017 8RFQ Date:Q4:2018 8Release Date:Q4:2018 8Start Date:Q1:2020 8Completion Date: Q3:2022 Click here for more information