Jun 07: 8Project Name: Greenfield Gas Pipeline
8Project Cost: Rs 2700 crore
8Project Description: The owner has hired the PMC contractor to construct a new gas pipeline. The length of the pipeline is 400 km with a 36”diameter.
8Project Event: RFQ for the 150 Km pipeline laying work is expected by August 2018.
8Expenditure Approval: Q3/2015
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q3:2016
8Completion Date: Q4:2020
Click here for more details

8Business Opportunity for a Maintenance Contractor
The owner is planning to float a short term annual maintenance contract for PLCs in its refinery for a tenure of three years.