Jun 06: Ammonia-Urea Energy Saving Project 8Cost - Rs 217 Crore 8Project Event: The proposal for a term of references has been granted and tender for major equipment is likely to be released in July or August 2018. Click here for more information NPK-SSP & Sulphuric Acid Expansion Project 8Cost - Rs 15 Crore 8Project Event: RFQ for a contractor is likely to be released after environmental clearance. The public hearing has completed but environmental clearance is due. the reason of delay in the environmental clearance is international specification added in Indian pollution control specifications, The company repeatedly gave presentations for cleareance, but rejected so far. Click here for more information Single Super Phosphate Fertilizer Greenfield Project 8Cost - Rs 8 Crore 8Project Event: Shortlisting process for EPC contractor is ongoing. Equipment requirement coming up Click here for more information