Rs 175 crore bottling plant: RFQ for EPC contractor is expected by August 2018.
Jun 06: 8Project Name: Greenfield LPG Bottling Plant Project
8Project Cost: Rs 175 crore
8Project Description: The owner is planning to relocate an existing LPG plant with a capacity of 120 TMTPA along with a 48 slot automatic electronic carousal and attendant downstream facilities. It has hired a consultant for  pre-feasibility studies.
8Project Event: RFQ for EPC contractor is expected by August 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Aug/2018
8Release Date: sep/2018
8Start Date: Q4:2018
8Completion Date: Q4:2020