Rs 250 crore gathering pipeline: LSTK contractor in August
Jun 05: 8Project Name: Pipeline Development 8Project Cost: Rs 260 crore. 8Project Description New: The owner has hired an EPCM contractor for the construction of a gathering pipeline in Assam. The project involves laying of 900 mm dia. Currently, the project is in pre-clearance phase. The EIA consultant for the project has already been hired. Moreover, the project will further be executed on LSTK basis. A slight delay is expected in TOR grant for the project as the applicability of the EIA Notification, 2006 has not been yet established till now from the Environment ministry. Moreover, the wildlife clearance is still pending for the project. 8Project Event New: RFQs for hiring an LSTK Contractor from the EPCM contractor's end is expected by August 2018. 8Expenditure Approval: Q4/2017 8RFQ Date: Aug/2018. 8Release Date: Oct/2018. 8Date: Jun/2019 8Completion Date: Dec/2020 Click here for more details and key contacts