Rs 1300 crore exploratory drilling: Third party rig to be deployed
Jun 04: 8Project Name: Drilling Field Development
8Project Cost: Rs 1300 crore.
8Project Description New: Owner's RFQs for civil works for 48 well exploratory drilling are out. The project will be rolled out in a phase-wise manner The drilling will be carried out using third-party rigs. There are 3 drilling rigs available with ONGC Jorhat Asset but these are already deployed. Currently, the project is in pre-clearance phase and EIA report preparation is still going on. Further RFQ for the project is expected shortly.
8Project Event New: RFQ for hiring a drilling rig is expected by September instead of June 2018.
8Project Event Old: RFQs for the hiring an EPC contractor for pipeline and gas grid network part are expected by June instead of May 2018.
8Expenditure Approval: Q2/2017
8RFQ Date: Sep/2018.
8Release Date: Oct/2018.
8Date: Jun/2019
8Completion Date: Dec/2021
Click here for more details for key  contacts and other project parameters


**********************************