Refinery expansion: RFQ for the Consultant for preparation of cost estimate for all unit is expected by July 2018
Jun 04: 8Project Name: Refinery Expansion Project 8Project Cost: Rs 27000 crore 8Project Description: The owner has appointed a DFR consultant. DFR will be completed by Q1 2019. At present project is in pre-planning stage and pre-project activities are going on. A slight delay in the selection of the contractor. 8Project Event: RFQ for the Consultant for preparation of cost estimate for all unit is expected by July 2018. RFQ for the surveying work is expected by August 2018. 8Expenditure Approval: Q3:2017 8RFQ Date: Jul/2018 8Release Date: Aug/2018 8Start Date: Q1:2019 8Completion Date: Q2:2023 Click here for more details for full project configuration and key contacts