Spurline project: RFQ for EPC contractor in August
May 31: 8Project Name: Spurline Pipeline Project 8Project Cost: Rs 25 crore 8Project Description: Gujarat Gas Limited is planning to lay a Natural gas spur line with a capacity of 1.29 MMSCMD along with the length of 19.1 Km for city gas purposes. It is envisaged that initially, the tap off connectivity shall be from GAIL Receiving Terminal. Gujarat Gas Limited has awarded the work to a private company for carrying out Reconnaissance Survey, Detailed Engineering Route Survey, Soil Investigation, Soil Resistivity and Cadastral Survey including obtaining Statutory Clearances and ROU Acquisition. Recently, a TOR was submitted but was returned on account of incomplete documentation. 8Project Event: RFQ for EPC contractor is expected by August 2018. 8Expenditure Approval: Q4:2016 8RFQ Date: Aug/2018 8Release Date: Sep/2018 8Start Date: Q1:2019 8Completion Date: Q4:2020 Click here for more details for more