May 31: 8Project Name: Refinery INDMAX Project 8Project Cost: Rs 4300 crore 8Project Description: The owner has appointed an EPC contractor and along with the licensor, they are carrying out engineering activities for an INDMAX unit. RFQ for equipment is already out. At present civil work is going on. ThyssenKrupp has got the contract of mechanical work for the FCC unit. RFQ for the mechanical work for the NHT and SRU is already out. 8Project Event: RFQ for the mechanical work for the Catalytic Reformer Unit (CRU) and Selective Desulphurisation Unit (SDS) is expected by August 2018. 8Expenditure Approval: Q3:2016 8RFQ Date: Aug/2018 8Release Date: Sep/2018 8Start Date: Q4:2017 8Completion Date: Q2:2020 Click here for more details for more contacts