All content in this website is sourced legitimately

Page No: 1
Refinery INDMAX Project: RFQ for the mechanical work for CRU and SDS in August
May 31: 8Project Name: Refinery INDMAX Project
8Project Cost: Rs 4300 crore
8Project Description: The owner has appointed an EPC contractor and along with the licensor, they are carrying out engineering activities for an INDMAX unit. RFQ for equipment is already out. At present civil work is going on. ThyssenKrupp has got the contract of mechanical work for the FCC unit. RFQ for the mechanical work for the NHT and SRU is already out.
8Project Event: RFQ for the mechanical work for the Catalytic Reformer Unit (CRU) and Selective Desulphurisation Unit (SDS) is expected by August 2018.
8Expenditure Approval: Q3:2016
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2017
8Completion Date: Q2:2020
Click here for more details for more contacts


**********************************

Back  |  Top