Platform trunkline modification: EPC contractor by Q4, 2018
May 29: 8Project Name:  Platform Trunkline Modification
8Project Cost: Rs 80 crore
8Project Description New: ONGC is planning modification in its existing BPB Platform Hazira Trunkline  Six companies have participated in the EOI. The gas pipeline supplies gas from offshore process platforms to the Gas Processing plant.
8Project Event New: RFQs for hiring an EPC contractor for the pipeline is expected by Q4 2018.
8Expenditure Approval: Q3/2018
8RFQ Date: Q4/2018
8Release Date: Q4/2018
8Start Date: Q1/2019
8Completion Date: Q4/2019