May 28: 8Project Name: Offshore Platform Trunkline Modification 8Project Cost: Rs 250 crore 8Project Description: The Promoter is planning modification in its existing Offshore Platform Trunkline having an overall length of 230 km. The promoter had invited an EOI for providing consultancy services for protection measures for gas pipelines. The EOI seems to have attracted a lot of parties with nearly 6 parties interested in the job. The gas pipeline supplies gas from offshore process platforms to an Onshore terminal. 8Project Event: RFQs for hiring an EPC contractor for pipelines is expected by Q4 2018. 8Expenditure Approval: Q3/2018 8RFQ Date: Q4/2018 8Release Date: Q4/2018 8Start Date: Q1/2019 8Completion Date: Q4/2019 Click here for more details