Software Updates : Power Projects
May 28: 8Project Name: Greenfield Hydroelectric Project
8Project Cost: 3500 crores
8Project Description: Owner is carrying out the survey and investigations activities for a 300 MW greenfield hydroelectric project. Further bids are expected soon.
8Project Event: RFQs for drilling and drifting works are expected by Q3 2018.
8Expenditure Approval: Q1:2019
8RFQ Date: Q3:2018
8Release Date: Q3:2018
8Start Date: 2020
8Completion Date: 2026
Click here for more information
8Project Name: Thermal Power Expansion Project
8Project Cost: 11000 crores
8Project Description: Promoter along with an EPC Contractor has completed the land leveling and grading activities for a 1980 MW super-critical project. Further tenders are expected soon.
8Project Event: Tenders for erection and installation of ash handling plant is expected by Q3 2018
8Expenditure Approval: Q1:2017
8RFQ Date: Q3:2018
8Release Date: Q3:2018
8Start Date: Q2:2017
8Completion Date: Q4:2021
Click here for more information
8Project Name: Thermal Power Station Maintenance Project
8Project Cost: 12 crores
8Project Description: A JV company has planned a 30-day scheduled overhaul in the 2000 MW thermal power station. The mandatory jobs includes replacement of boiler pressure parts, checking of generator rotor, replacement of guide bearings of turbine, among others.
8Project Event: RFQs for overhaul of equipment are expected by the end of June 2018.
Click here for more information

**********************************