Rs 375 crore exploratory drilling programme: RFQ for the hiring of rig services is expected by August instead of June 2018
May 24: 8Project Name:  Drilling Field Development
8Project Cost: Rs 375 crore
8Project Description: The operators RFQs for hiring rig services for exploratory drilling of 13 wells have been delayed on account of environment clearance issues for the project. The equipment required for the project is casing pipes, drilling pipes, cementing services, drill bits, Xmas Tree and other oilfield chemicals. Further RFQs are expected shortly.
8Project Event:
-- RFQ for the hiring of rig services is expected by August instead of June 2018.
-- RFQs for the equipments and oilfield chemicals are expected by August instead of June 2018.
-- RFQs for hiring wireline and cementing services is expected by September 2018.
8Expenditure Approval: Q4/2016
8RFQ Date: Aug/2018
8Release Date: Oct/2018
8Start Date: May/2019
8Completion Date: May/2021