Barauni-Guwahati Greenfield Gas Pipeline: What is the latest status, who are the key contacts?
May 23: 8Project Name: Barauni - Guwahati Greenfield Gas Pipeline (GAIL) 8Project Cost: Rs 4015 Crore 8Project Description: Petroleum and Natural Gas Regulatory Board (PNGRB) has accorded the Provisional Acceptance to GAIL for the proposal for laying, building, operating or expanding Barauni-Guwahati natural gas pipeline. The capacity of the pipeline is 1.85 MMSCMD. The total length of the pipeline is estimated to be about 750 km of 24-inch in diameter across the states from Bihar to Assam. RFQ for the PFR consultant is already out. A consultant will be hired to take care of land acquisition and attendant issues. 8Project Event: RFQ for land acquisition consultant is expected by June 2018. RFQ for survey work is expected by August 2018. 8Expenditure Approval : Q4:2017 8RFQ Date : Aug/2018 8Release Date: Sep/2018 8Start Date : Q1:2019 8Completion Date : Q1:2022 Click here for more details. Subscribe with us for continuous updates on this project, along with key contacts, project configurations and equipment and service requirement going ahead.