May 22: NPK Fertilizer Greenfield Project  
8Cost - Rs 1517 Crore
8Project Event: RFQ for EPC contractor was floated in February 2017 and price bid has been opened, Finalization is due in two weeks, there has been a delay due to discussions. the tender for equipment is likely to be released in June 2018.
 
Click here for more information
Ammonia-Urea Energy Saving Project
       
8Cost - Rs 347 Crore
8Project EventEOI has already been released for an LSTK contractor in November 2017 but an NIT has not been floated yet, and that is likely in June 2018.
 
Click here for more information
SSP Fertilizer Greenfield Project   
8Cost - Rs 90 Crore
8Project EventRFQ for an LSTK contractor was released in March 2018 and evaluation process is ongoing, price bid has not been opened yet, Tender for equipment is likely to be released in August 2018.
Click here for more information


**********************************