May 21: 8Project Name: Greenfield LPG pipeline project
8Project Cost: Rs 5000 crore
8Project Description: The owner along with PMC contractor has divided up the pipeline into three stretches, 650 km (approx) each for contracting purposes. RFQ for the compressors and drivers is already out. Further RFQs are expected soon.
8Project Event: RFQ for the mainline pipes and stations valves are expected by August 2018.
8Expenditure Approval: Q3/2016
8RFQ Date: Aug/2018
8Release Date: Oct/2018
8Start Date: Q3:2018
8Completion Date: Q3:2021