Rs 650 crore Greenfield POL Terminal Project: RFQ for the PMC contractor is expected by mid of the June 2018
May 18: 8Project Name: Greenfield POL Terminal Project 8Project Cost: Rs 650 crore 8Project Description: The owner is planning to install Greenfield Petroleum Storage Terminal. The EIA and PFR consultants have been hired. Investment of Rs 10 crore has already been done. 8Project Event: RFQ for the PMC contractor is expected by mid of the June 2018. RFQ for equipment supply is expected by August 2018. 8Expenditure Approval: Q3/2017 8RFQ Date: Aug/2018 8Release Date: Sep/2018 8Start Date: Q4:2018 8Completion Date: Q4:2020 Click here for more details for key contacts, project configurations and other additional information