Rs 300 crore cogeneration Unit: EPC contractor RFQ in Q3, 2018
May 17: 8Project Name: Cogeneration Unit Addition
8Project Cost: Rs 300 crore
8Project Description: The owner is planning the expansion of onshore oil & gas processing plant by establishing Additional Cogeneration Unit and an Enhanced Reactive Thermal Oxidizer. The new Gas Turbine based Cogeneration power plant will have a capacity of 20 MW. An EIA consultant has already been hired for the project. The project will be implemented on EPC basis. Further RFQs are expected shortly.
8Project Event: RFQ for the hiring of an EPC contractor is expected by Q3:2018.
8Expenditure Approval: Q3/2016
8RFQ Date: Q3/2018
8Release Date: Q3/2018
8Start Date: Feb/2020
8Completion Date: Dec/2021