Rs 1200 crore gas pipeline: PMC contractor RFQ in August now
May 16: 8Project Name: Greenfield Natural Gas Pipeline Project
8Project Cost: Rs 1200 crore
8Project Description: The owner is planning a 200 km 36" pipeline with associated facilities such as Sectionalized Valve (SV), dispatch terminal and receiving terminals and intermediate pigging stations. A slight delay in the selection of PMC contractor is noticed due to forest clearance issues.
8Project Event: RFQ For PMC contractor is to be expected by August instead of May 2018.
8Expenditure Approval: Q4/2016
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2018
8Completion Date: Q4:2020