May 15: 8Project Name: Offshore Field Development
8Project Cost: Rs 450 crore.
8Project Description: The owner's field development plan for a DSF-2016 Round block was reviewed by DGH. The project involves drilling of 2 wells, installation of one wellhead platform and laying of a 4-inch 10km pipeline. Currently, the project is in clearance stage. The whole project is expected to be executed by lump sum Integrated Project Mangement Consultant and Engineering Procurement Installation and Commissioning model.
8Project Event: RFQ for hiring IPM consultant and EPIC contractor is expected by July 2018 instead of June 2018.
8Expenditure Approval: Q2/2016.
8RFQ Date: Jul/2018.
8Release Date: Sep/2018.
8Date: Q1/2021
8Completion Date: Q2/2022