May 15: 8Project Name: Captive Solar Power Unit 8Project Cost: Rs 50 crore 8Project Description: Owner's RFQ for 5 MW captive Solar Power Unit has been delayed on account of clearance issues. As of now feasibility report for the project is under preparation. The project will have to be executed on turnkey basis. 8Project Event: RFQ for hiring the LSTK contractor for the project is expected by August 2018 instead of June 2018. 8Expenditure Approval: Nov/2017 8RFQ Date: Aug/2018 8Release Date: Sep/2018 8Start Date: Q4/2018 8Completion Date: Q2/2019 Click here for more information