May 15: 8Project Name: Hydroelectric Greenfield Project 8Project Cost: 4000 crores 8Project Description: Owner along with an EIA consultant is planning to construct a greenfield 500 MW hydroelectric plant. Promoter has not yet decided whether to come in package wise mode or EPC mode. Further bid are expected soon. 8Project Event: RFQs for a package wise or an EPC contract are expected by Q3 2018. 8Expenditure Approval: Q4:2018 8RFQ Date: Q3:2018 8Release Date: Q3:2018 8Start Date: 2020 8Completion Date: 2025 Click here for more information 8Project Name: Thermal Power Plant - Annual Maintenance Contract Project 8Project Cost: 1 crore 8Project Description: A JV company is getting delayed in bring out an annual maintenance RFQ for electrical and C&I equipment in a 1980 MW super-critical thermal power plant, due to lack of approval from NTPC headquarter. Furthers bids are expected soon. 8Project Event: RFQs for annual maintenance contract for electrical and C&I equipment are expected to be out by Q3 2018, instead of May 2018. 8Expenditure Approval: Q2:2017 8RFQ Date: Q3:2018 8Release Date: Q3:2018 8Start Date: Q4:2018 8Completion Date: Q4:2019 Click here for more information 8Project Name: Thermal Power Project - Installation of FGD 8Project Cost: 1500 crores 8Project Description: Promoter's bid for Wet Flue Gas Desulphurisation (WFGDs) in the 2000 MW super-critical thermal power complex has been delayed on account of time taken in the execution of the pre-bid meeting. Further bid for the supply, installation and commissioning of the WFGDs are expected soon. 8Project Event: RFQs for the supply of WFGDs are expected to be out by July 2018, instead of May 2018. 8Expenditure Approval: Q3:2017 8RFQ Date: Jul/2018 8Release Date: Jul/2018 8Start Date: Q2:2020 8Completion Date: Q3:2021 Click here for more information