POL Terminal and storage projects: Business opportunities ahead
May 14: 8Project Name: POL Terminal Project
8Project Cost: Rs 190 crore
8Project Description: Owner is planning to do augmentation in 25000 KL depot by installing intermediate pumping cum tap off facilities, receipt station and pigging facilities. Mantec Consultants Private Limited was appointed as PFR consultant.
8Project Event: RFQ for EPMC contractor is expected by August 2018.
8Expenditure Approval: Q2/2017
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2018
8Completion Date: Q3:2021
Click here for more details

8Project Name: Greenfield POL Terminal Project
8Project Cost: Rs 800 crore
8Project Description: Onwer is planning to set up a new POL Terminal at a port. The proposed Terminal shall fully comply with PESO, OISD (Oil Industry Safety Directorate) standards (mainly 244) and other statutory requirements. The construction capacity of storage tanks will be 161436 KL. EIA and PFR consultants have already been appointed.
8Project Event: RFQ for a PMC contractor is expected by August 2018.
8Expenditure Approval: Q2/2017
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2018
8Completion Date: Q4:2020
Click here for more details

8Project Name: Terminal Project
8Project Cost: Rs 150 crore
8Project Description: Owner is planning to amend the existing capacity of its POL terminal from 216874 KL to 275365 KL. PFR consultant has already been appointed.
8Project Event: RFQ for EPMC contractor is expected by June 2018.
8Expenditure Approval: Q3/2017
8RFQ Date: Jul/2018
8Release Date: Aug/2018
8Start Date: Q4:2018
8Completion Date: Q3:2021
Click here for more details

8Project Name: Greenfield POL Terminal
8Project Cost: Rs 600 crore
8Project Description: Owner has hired an EIA consultant for a POL terminal with a capacity of 350220 KL.
8Project Event: RFQ for the PMC contractor is expected by August 2018.
8Expenditure Approval: Q3/2017
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2018
8Completion Date: Q4:2021
Click here for more details

8Project Name:Brownfield LPG Bottling Plant Expansion
8Project Cost: Rs 100 crore
8Project Description: Owner is planning to expand its LPG bottling plant capacity from 1000 MT to 2500 MT by constructing new 3 X 500 MT mounded storage vessels. Environmental clearance was granted by June 2017. Some of the equipment is ordered and rest of the equipment is under tendering. At present mechanical work is going on.
8Project Event: RFQ for the instrumentation and electrical work is expected by July 2018.
8Expenditure Approval: Q1/2017
8RFQ Date: Jul/2018
8Release Date: Aug/2018
8Start Date: Jul/2017
8Completion Date: Q1:2019
Click here for more details


**********************************