Downstream petrochemical leads for the day
May 11: Along with our project monitoring software, you get a dedicated analyst. Should you want something checked out or you want a clarification on something we have given, just pick up the phone and call him. He will get back to you with the correct answers.
8Project Name: POL Terminal Expansion Project (IOCL)
8Project Cost: Rs 90 Crore
8Project Description: Owner is planning to expand its POL Terminal. A PFR consultant has been selected.
8Project Event: RFQ for the PMC contractor is expected by July 2018.
8Expenditure Approval : Q3:2017
8RFQ Date : Jul/2018
8Release Date: Aug/2018
8Start Date : Q3:2018
8Completion Date : Q4:2019
Click here for more details.
8Project Name: Refinery Greenfield Propylene Derivative Petrochemical Project
8Project Cost: Rs 5000 crore
8Project Description: The PMC contractor and licensor are carrying out engineering activities to install a Propylene Derivatives Petrochemical complex. Miscellaneous civil and structural work is already out and there is a slight delay in mechanical work. Further RFQs are coming soon.
8Project Event: RFQ for the Instrumentation works for Acrylic acid, Acrylates and offsite is expected by last week of June 2018.
8Expenditure Approval : Q2:2015
8RFQ Date : Jun/2018
8Release Date: Jul/2018
8Start Date : Q4:2015
8Completion Date : Q3:2019
Click here for more details.
8Project Name: Refinery BS VI Motor Spirit Block Upgradation
8Project Cost: Rs 3500 crore
8Project Description: Owner has hired an EPCM contractor to carry out engineering activities to upgrade its BS-V Motor spirit block to BS-VI Motor Spirit block. involving the construction of a Naphtha hydrotreater unit, Continuous catalytic reformer (CCR) unit, and a Light naphtha isomerization unit. RFQ for the procurement of equipment is already out. There will be a slight delay in erection and installation work due to delay in equipment procurement.
8Project Event: RFQ for erection and installation works is expected by July 2018 instead of March 2018.
8Expenditure Approval : Q2:2016
8RFQ Date : Jul/2018
8Release Date: Aug/2018
8Start Date : Q4:2016
8Completion Date : Q4:2019
Click here for more details.
8Business Opportunity for Equipment Suppliers
8Owner is planning to float a contract for 600 pump spares in a refinery for a time period of one year.
Click on Details for more


**********************************