Software Updates : Power Projects
May 11: 8Project Name: Thermal Power Station Long Term Contract
8Project Cost: 10 crores
8Project Description: Promoter is preparing the bid document for a long term contract (LTC) for an ash handling plant (preventive maintenance and round the clock maintenance) of 2000 MW Thermal Power Station. Further bids are expected soon.
8Project Event: RFQs for LTC of an ash handling system are expected by the mid May 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 17/May/2018
8Release Date: 25/May/2018
8Start Date: Sep/2018
8Completion Date: Sep/2021
Click here for more information
8Project Name: Hydro Power Station - Renovation, Modernization and Life Extension Project
8Project Cost: 80 crore
8Project Description: Owner is getting delayed in the renovation works for a 150 MW Hydo Power Station due to the bad weather conditions. Owner will come out with a bid for supply of brake-jack system and short lead equipment for runner parts soon.
8Project Event: RFQs for brake-jack system and short lead equipment of runner are expected by June 2018, instead of May 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: Jun/2018
8Release Date: Jun/2018
8Start Date: Q2:2017
8Completion Date: Q1:2020
Click here for more information
8Project Name: Thermal Power Plant - O&M Contract
8Project Cost: 2 crores
8Project Description: Owner is preparing the notice inviting tender document for an O&M contract for electrical equipment in the 2000 MW thermal power complex. The contract tenure will be of two years.
8Project Event: RFQs for O&M of electrical equipment are expected by Q3 2018, instead of May 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Q3:2018
8Release Date: Q3:2018
8Start Date: Aug/2018
8Completion Date: Aug/2020
Click here for more information

**********************************