Software Updates : Power Projects
May 09: 8Project Name: Maintenance of BoP and WTP in Thermal Power Station
8Project Cost: 6 crores
8Project Description: Owner is finalizing the bid document for a maintenance (running and breakdown) of balance of plant and water treatment plant of a 2000 MW thermal power plant. Further bid are expected soon.
8Project Event: RFQs for a triennial maintenance of BoP and water treatment plant are expected by the mid May 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 15/May/2018
8Release Date: 31/May/2018
8Start Date: Oct/2018
8Completion Date: Oct/2021
Click here for more information
8Project Name: Greenfield Pumped Storage Project
8Project Cost: 6000 crore
8Project Description: Promoter along with a PFR consultant is planning to construct a 2500 MW pumped storage hydro power station. Owner is expected to come out with a bid for a consultant for the preparation of the detailed project report.
8Project Event: RFQs of a consultant for preparation of the detailed project report are expected by Q3 2018.
8Expenditure Approval: Q4:2018
8RFQ Date: Q3:2018
8Release Date: Q3:2018
8Start Date: 2020
8Completion Date: 2025
Click here for more information
8Project Name: Thermal Power Maintenance Project (Unit-2)
8Project Cost: 12 crores
8Project Description: Owner has planned a 35-day scheduled boiler overhaul in the 2500 MW thermal power station. The mandatory job includes cleaning of boiler, water tubes, boiler drum, dearator, checking and replacement of pressure parts of boiler, inspection of wind box supports and its expansion joints, replacement of the journal bearing and thrust bearing of low pressure turbine, replacement of pipes, among others.
8Project Event: RFQ for equipment required is expected by the end of May 2018.
Click here for more information

**********************************