Rs 900 crore refinery captive power plant: RFQ for civil works and short lead turbine equipment soon
May 08: 8Project Name: Refinery Greenfield Captive Power Project 8Project Cost: Rs 900 crore 8Project Description: The LSTK contractor is likely to float bids for civil works and transportation services for a 75 MW captive power plant. Bid for civil work and allied transportation services was delayed due to delay in survey work. Further bids are expected soon. 8Project Event: RFQ for civil works and related transportation activities along with short lead equipment for gas turbine is expected by June instead of May 2018. 8Expenditure Approval : Q4:2016 8RFQ Date : Jun/2018 8Release Date: Jul/2018 8Start Date : Q4:2018 8Completion Date : Q4:2020 Click here for more details for full details