Rs 700 crore drilling programme: RFQs for EPC contractor by June, rig services by August
May 07: 8Project Name:  Drilling Field Development
8Project Cost: Rs 700 crore
8Project Description: The owner's RFQs for an Early Production System and laying of Infield Pipelines is expected soon. The project involves development drilling of 40 wells, construction of 10 Early Production System and laying of Infield Pipelines. Currently, the owner is going through the EIA consultant hiring process.
8Project Event: RFQs for hiring an EPC Contractor and other Oilfield services is expected by June 2018.
RFQs for hiring rig services is expected by August 2018.
8Expenditure Approval: Q1/2018
8RFQ Date: Jun/2018
8Release Date: Aug/2018
8Start Date: May/2019
8Completion Date: Dec/2021