Software Updates : Power Projects
May 07: 8Project Name: Greenfield Hydroelectric Project
8Project Cost: 1500 crores
8Project Description: Promoter has submitted the detailed project report to the CEA for techno-economic clearance for a 150 MW greenfield hydro power station. A bid for civil works is expected soon.
8Project Event: RFQ for civil works is expected to be out in the Q3 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Q3:2018
8Release Date: Q3:2018
8Start Date: Q1:2020
8Completion Date: Q2:2025
Click here for more information
8Project Name: Boiler R&M in Thermal Power Station
8Project Cost: 200 crore
8Project Description: Owner plans to carry out boiler renovation and modernisation (R&M) in the 3000 MW thermal power station. Bid for an R&M package is expected to come out soon.
8Project Event: RFQs for boiler R&M package is expected to come out by the mid May 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 15/May/2018
8Release Date: 20/May/2018
8Start Date: Q3:2018
8Completion Date: Q2:2019
Click here for more information
8Project Name: Thermal Power Station Maintenance Project 
8Project Cost: 20 crores
8Project Description: A JV company has planned a 25-days boiler scheduled annual maintenance in the 800 MW thermal power station. The mandatory job includes servicing of burner system, overhauling of ID, FD and scanner air fans, replacement of seals, support bearings, casing, valves, overhauling of boiler pressure parts, servicing of soot blowers, replacement of boiler tube, repair of coal nozzle, repair of ducts and dampers, servicing of boiler fill pump, among others.
8Project Event: RFQs for required equipment are expected by June 2018.
Click here for more information

**********************************