May 03: 8Project Name: Oil Field Development
8Project Cost: Rs 1200 crore.
8Project Description: RFQs for rigs and EPC contractor for owner's 100 well development drilling plan have been delayed a bit. The process of hiring an EPC contractor for the Field Gas Gathering Station (FGGS) and and an attached pipeline laying part is expected to begin soon. RFQ for the Rigs, Blow-Out Controller, Xmas Trees, Cementing, Wireline, Drill Collar etc will come out too.
8Project Event: RFQ for an EPC contractor for FGGS and the pipeline network is expected by August instead of May 2018.
RFQ for hiring services for rigs and equipment is expected by September 2018 instead of May 2018.
8Expenditure Approval: Q2/2017.
8RFQ Date: Aug/2018.
8Release Date: Sep/2018.
8Date: Q1/2019.
8Completion Date: Q1/2022.