RIL's LNG offtake to fall soon
May 02: The RIL's DTA refinery gasifiers under petcoke gasification project are currently under stabilization and optimization process.
8They normally take 3-6 months. Hence, commercialization is expected in the current quarter.
8The SEZ refinery units are under commissioning and by Q3FY19, the entire petcoke gasification would be commercially operational.
8RIL will cut LNG consumption that extent by these timelines.
8LNG offtake will come down as a result