Refinery expansion and upgradation: RFQ for the mechanical work for the NHT and SRU is expected by June 2018
Apr 26: 8Project Name: Refinery expansion and upgradation
8Project Cost: Rs 4000 crore
8Project Description: The refiner along with the EPC contractor and Licensors are carrying out engineering activities to construct new units. RFQ for equipment is already out. At present civil work is going on. Some contracts for mechanical work has been awarded (find out more)
8Project Event: RFQ for the mechanical work for the NHT and SRU is expected by June 2018.
8Expenditure Approval : Q3:2016
8RFQ Date : Jun/2018
8Release Date: Jul/2018
8Start Date : Q4:2017
8Completion Date : Q2:2020
Click here for more details for project configurations, design capacity, unit-wise details and key contacts.


**********************************