Rs 900 crore pipeline: RFQ for the PMC contractor is expected by June 2018
Apr 20: 8Project Name: Greenfield LPG Pipeline Project 8Project Cost: Rs 900 crore 8Project Description: The owner is planning to lay the pipeline with a length of 700 km approximately. There is a slight delay in land acquisition in the route due to local agitation. 8Project Event: RFQ for the PMC contractor is expected by June 2018. 8Expenditure Approval : Q3:2015 8RFQ Date : Jun/2018 8Release Date: Jul/2018 8Start Date : Q4:2018 8Completion Date : Q4:2021 Click here for more details for pipeline configuration details and key contacts