Rs 900 crore pipeline: RFQ for the PMC contractor is expected by June 2018
Apr 20: 8Project Name: Greenfield LPG Pipeline Project
8Project Cost: Rs 900 crore
8Project Description: The owner is planning to lay the pipeline with a length of 700 km approximately. There is a slight delay in land acquisition in the route due to local agitation.
8Project Event: RFQ for the PMC contractor is expected by June 2018.
8Expenditure Approval : Q3:2015
8RFQ Date : Jun/2018
8Release Date: Jul/2018
8Start Date : Q4:2018
8Completion Date : Q4:2021