Refinery upgradation: RFQ for erection and installation work now expected by June 2018
Apr 18: 8Project Name: Kochi Refinery BS VI Motor Spirit Block Upgradation
8Project Cost: Rs 3313 Crore
8Project Description: The owner has hired an EPCM contractor for the purpose. There is a slight delay in erection and installation work due to delay in equipment procurement.
8Project Event: RFQ for the Pigging work is expected by May 2018.
 RFQ for erection and installation work is expected by June 2018 instead of March 2018.
8Expenditure Approval : Q2:2016
8RFQ Date: May/2018
8Release Date: Jun/2018
8Start Date : Q4:2016
8Completion Date : Q4:2019