Rs 5000 crore greenfield LNG Terminal: RFQ for equipment in July, 2018
Apr 13: 8Project Name: Greenfield LNG Terminal 8Project Cost: Rs 5000 Crore 8Project Description: Owner is planning to install an LNG Floating Storage and Regasification Unit (FSRU). The EPC contractor is already in. The FSRU design has been finalized and is expected to take delivery of the same by December 2018. 8Project Event: RFQ for Equipment is expected by July 2018. 8Expenditure Approval : Q2:2017 8RFQ Date : Jul/2018 8Release Date: Sep/2018 8Start Date : Q3:2018 8Completion Date : Q1:2020 Click here for more details for project configuration and key contacts.