Refinery debottlenecking: RFQs for electrical and instrumentation work in June
Apr 12: 8Project Name: Refinery Debottlenecking Greenfield 8Project Cost: Rs 2500 crore 8Project Description: Engineering activities are on for the debottlenecking of the refinery. RFQ for the equipment, erection, and installation work is already out. 8Project Event: RFQ for electrical and instrumentation work is expected by June 2018. 8Expenditure Approval : Q4:2016 8RFQ Date : Jun/2018 8Release Date: Jul/2018 8Start Date : Q2:2017 8Completion Date : Q4:2018 Click here for more details on refinery configuration, product slates, utility matrix, unit details and key contacts.