Apr 05: 8Project Name: C2/C3 Shutdown Maintenance Project 8Project Cost: Rs 20 Crore 8Project Description: Owner is planning to shut down its C2/C3 unit for two months.This shutdown will expect to start in the month of August. 8Project Event: RFQ for a contractor is expected by June 2018. 8Expenditure Approval : Q4:2017 8RFQ Date : Jun/2018 8Release Date: Jul/2018 8Start Date : Aug/2018 8Completion Date : Oct/2020 Click here for more details. 8Project Name: Refinery Maintenance Shutdown Project 8Project Cost: Rs 20 Crore 8Project Description: A refinery has hired a PMC contractor to do the maintenance shut down of crude distillation unit and FCC unit from the month of July 2018 for 30 days at Manali refinery. 8Project Event: RFQ for Instrumentation work is expected by May 2018. 8Expenditure Approval : Q1:2018 8RFQ Date : May/2018 8Release Date: Jun/2018 8Start Date : Jul/2015 8Completion Date : Aug/2019 Click here for more details.Another Visakhapatnam Refinery Maintenance Shutdown Project 8Project Cost: Rs 20 Crore 8Project Description: A shut down is envisaged in three crude distillation units of Visakhapatnam refinery for 3-4 weeks in the month of July to September while the rest of the secondary units have been planned to be streamlined for the Euro- VI grade fuel production process. 8Project Event: RFQ for the contractor is expected by May 2019. 8Expenditure Approval : Q1:2018 8RFQ Date: May/2019 8Release Date: Jun/2019 8Start Date : Jul/2019 8Completion Date : Sep/2019 Click here for more details.