Software updates: Oil and Gas Projects.
Apr 04: 8Project Name: Exploratory Drilling
8Project Cost: Rs 800 Crore.
8Project Description: Promoter is planning exploratory drilling of 25 wells in an oilfield. The drilling services for the project will be hired soon. RFQ for the following equipment are expected shortly for Cementing Unit, Blow Out Preventer, Pressure Gauge, Valves and Well Chemicals.
8Project Event: RFQ for the equipment is expected by June 2018 instead of March 2018 due to the environment clearance delay.
RFQs for the drilling services is expected by August 2018.
8Expenditure Approval: Q3/2016
8RFQ Date: Jun/2018
8Release Date: Sep/2018
8Start Date: Q1/2019
8Completion Date: Q4/2023
Click here for more details

8Project Name: GCS, Treatment Facility and Development Drilling
8Project Cost: Rs 1000 crore.
8Project Description: Promoter is planning development drilling of oil wells for an onshore block. Promoter will conduct a development drilling programme and equipment requirement will be Xmas Trees, Manifolds, DG Sets, Compressor, HSD.
8Project Event: RFQs for equipment are expected by June instead of April 2018.
8Expenditure Approval: Q2/2015
8RFQ Date: Jun/2018
8Release Date: Jul/2018
8Start Date: Q3/2018
8Completion Date: Jul/2021
Click here for more details

8Project Name: Oil Field Development
8Project Cost: Rs 220 crore
8Project Description: The Promoter is planning 9 well Exploration and Development drilling programme. Besides drilling of wells, construction of Group Well Head facility near the new wells is also being planned. An EIA consultant has already been hired. Further RFQs are expected shortly.
8Project Event: RFQ for the hiring of drilling-related material is expected by July 2018.
8Expenditure Approval: Q4/2017
8RFQ Date: July/2018
8Release Date: Aug/2018
8Start Date: Oct/2019
8Completion Date: Oct/2021