Apr 04: 8Project Name: Thermal Power Expansion Project 8Project Cost: 10000 crores 8Project Description: The owner is going on with construction and erection activities of a super-critical thermal power complex with a capacity of 1600 MW at thermal power station. Bid for an FGD package is expected soon. 8Project Event: RFQs for a Flue Gas Desulphurisation Unit are expected in May 2018. 8Expenditure Approval: Sep/2014 8RFQ Date: May/2018 8Release Date: Q3:2018 8Start Date: Oct/2015 8Completion Date: Q3:2019 Click here for more information 8Project Name: Hydroelectric Power Station - Maintenance Contractor Project 8Project Cost: 3 crores 8Project Description: The owner will come out with a bid for maintenance contractor of hydro-mechanical and power house (electrical) equipment. Further RFQs are expected soon. 8Project Event: RFQs for a biennial maintenance contractor for HM and electrical equipment are expected by June 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: Jun/2018 8Release Date: Jul/2018 8Start Date: Q4:2018 8Completion Date: Q4:2020 Click here for more information 8Project Name: Thermal Power Station Maintenance Project 8Project Cost: 20 crores 8Project Description: The developer has planned a 31-day scheduled maintenance in the 1500 MW thermal power plant covering an annual overhaul of boiler and turbine. The mandatory job includes refurbishment of pressure parts of boiler, replacement of turbine rotating blades, burner refurbishment, replacement of spare parts of turbine, among others. 8Project Event: RFQs for equipment required are expected by mid of May 2018. Click here for more information