Apr 03: 8Project Name: Greenfield Pipeline Project 8Project Cost: Rs 9500 Crore 8Project Description: An owner has hired a private company as the EPCM contractor for Phase-1 Natural Gas Pipeline. A pipeline is under construction. In phase-I, a private company was hired as an EPCM contractor, and construction work is slated to be completed by December. Phase - II is further divided into two stages stage-I and stage-II with two private company was hired as EPCM contractors respectively. Both stages will go hand in hand and the completion is to be expected by 2020. Recently a company has been hired as the laying contractor for the pipeline of phase-II, stage-I. 8Project Event: RFQ for Pre-commissioning activities for Phase-I is expected by June 2018. RFQ for procuring mainline pipes for Phase-II is expected by August 2018. RFQ for the laying contractor of phase-II, stage-II is expected by July 2018. 8Expenditure Approval : Q2:2015 8RFQ Date: Jun/2018 8Release Date: Jul/2018 8Start Date : Q4:2016 8Completion Date : Q3:2020 Click here for more details for key contacts and business development opportunities. Bio-refinery: RFQ for EPC contractor is coming up soon. 8Project Name: Greenfield 2G Bio-Ethanol Refinery 8Project Cost: Rs 650 Crore 8Project Description: An owner along with licensor Praj Industries Ltd. is planning to construct an ethanol plant based on the DBT-ICT 2G Ethanol technology developed indigenously to produce 100KL fuel-grade ethanol per day, primarily from biomass and will use approximately 400 tons of biomass per day. Engineers India Limited is appointed as the DFR consultant. 8Project Event: RFQ for EPC contractor is expected by July 2018. 8Expenditure Approval : Q3:2017 8RFQ Date: Jul/2018 8Release Date: Aug/2018 8Start Date: 2019 8Completion Date: 2022 Click here for more details. 8Project Name: LPG bottling plant project 8Project Cost: Rs 150 Crore 8Project Description: An owner is planning to install an LPG bottling plant with a capacity of 60000 MTPA by installing 10 X 6000 MT of mounded bullets for bulk LPG storage. 8Project Event: RFQ for Project Management Consultant is expected by June 2018. 8Expenditure Approval : Q3:2017 8RFQ Date: Jun/2018 8Release Date: Jul/2018 8Start Date : Q3:2018 8Completion Date : Q4:2019 Click here for more details. 8A spate of Bio-CNG plants is coming up. Click on Details to find key contacts and business development opportunities.