All content in this website is sourced legitimately

Page No: 1
Software Updates : Power Projects
Mar 28: 8Project Name: Super Thermal Power Greenfield Project Stage-1
8Project Cost: 10000 crores
8Project Description: The developer is going on with construction and erection activities for a 1800 MW brownfield super-critical thermal power plant. Further RFQs are expected soon.
8Project Event: RFQs for balance works of an offsite area - civil works package are expected by first week of April 2018.
8Expenditure Approval: Feb/2005
8RFQ Date: 7/Apr/2018
8Release Date: May/2018
8Start Date: 2005
8Completion Date: 2020
Click here for more information
8Project Name: Super Thermal Power Plant - O&M Contract
8Project Cost: 1.00 crores
8Project Description: The owner has floated a bid for its 2000 MW thermal power complex. The complex is under commercial operation. Further RFQ of a maintenance contract is expected soon.
8Project Event: RFQs for O&M of electrical equipment are expected by May 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: May/2018
8Release Date: Jun/2018
8Start Date: Aug/2018
8Completion Date: Aug/2020
Click here for more information
Township and office buildings: RFQs are expected in end of March 2018
8RFQ for construction of township and office buildings is expected by the end of March 2018. The owner is going on with evaluation of bids for a hydro-mechanical package. Further RFQs for infra works are expected soon.
Click here for more information

**********************************

Back  |  Top