Mar 28: Twelve well drilling programme: RFQs for Rigs, ETPs and Equipment to be out in April 8RFQ for equipment is expected by June 2018 for a 12 wells drilling project. The forest clearance for the project has not been submitted as yet as well. The mechanical equipment required would be Pump Skid, Degasser Skid, Hopper Skid, HSD Transfer Skid, Diesel Gensets, Super Charger Skid, Wellhead and Christmas Tree. Moreover, RFQs for rigs are expected by April end. Click here for more details Three well drilling programme: RFQs for Wireline and cementing services in May, equipment and contractor RFQs in April 8RFQs for wireline and cementing services for a three-well developmental drilling programme is expected in May 2018. RFQ for equipment and civil contractor were meant to come out in February and March this year for both but have now been delayed to April instead. Meanwhile, the rig for the project has also been finalized. Click here for more details 8Project Name:Oil Field Development: Fresh greenfield opportunity 8Project Cost: Rs 300 crore 8Project Description: The Promoter is planning exploratory drilling of 17 wells. The tentative targeted depth of the wells will be up to 5200m. The equipments required for the project will be casing pipes, drilling pipes, cementing services, drill bits, Xmas Tree and other oilfield chemicals. An EIA consultant has already been hired for the project. Further RFQs are expected shortly. 8Project Event: RFQ for the hiring of rig services is expected by Q3/2018. RFQs for the equipments and oilfield chemicals are expected by Q3/2018. 8Expenditure Approval: Q3/2017 8RFQ Date: Q3/2018 8Release Date: Q3/2018 8Start Date: Oct/2019 8Completion Date: Oct/2021 Click here for more details