Mar 27: 8Project Name: Refinery Shutdown Project
8Project Cost: Rs 20 Crore
8Project Description:  An owner is planning for a Shutdown from July 2018. This is a maintenance shutdown and it is for 30 days.
8Project Event: RFQ for an EPC contractor is expected by June 2018.
8Expenditure Approval : Q3:2017
8RFQ Date: Jun/2018
8Release Date: Jul/2018
8Start Date: Jul/2018
8Completion Date: Aug/2018
Click here for more details.

8Project Name: Depot Expansion Project
8Project Cost: Rs 150 Crore
8Project Description: An owner is planning to expand its Depot's storage capacity.
8Project Event: RFQ for PMC contractor is expected by June 2018.
8Expenditure Approval : Q3:2017
8RFQ Date: Jun/2018
8Release Date: Jul/2018
8Start Date : Q4:2018
8Completion Date : Q4:2023
Click here for more details.

8Project Name: Refinery DHDT Debottlenecking Project
8Project Cost: Rs 1810 Crore
8Project Description: An owner along with EPCM contractor and licensor is planning to expand its DHDT unit at its refinery. RFQ for the equipment is already out. At present civil work is going on.
8Project Event: RFQ for electrical and instrumentation work is expected by June 2018.
8Expenditure Approval : Q3:2017
8RFQ Date: Jun/2018
8Release Date: Jul/2018
8Start Date : Q1:2018
8Completion Date : Q1:2021