Mar 26: 8Project Name: Greenfield 2G Bio-Ethanol refinery
8Project Cost: Rs 500 Crore
8Project Description: An owner is planning to construct an ethanol plant based on the DBT-ICT 2G Ethanol technology developed indigenously to produce fuel-grade ethanol per day, primarily from biomass.
8Project Event: RFQ for PFR consultant is expected by June 2018.
8Expenditure Approval : Q3:2017
8RFQ Date: Jun/2018
8Release Date: Jul/2018
8Start Date : Q4:2018
8Completion Date : Q4:2021
Click here for more details.

8Project Name: Refinery Maintenance Shutdown Project
8Project Cost: Rs 20 Crore
8Project Description: An owner is going to undertake the shutdown of its unit in May. The shutdown is for 45 days.
8Project Event: RFQ for the contractor is expected by April 2019.
8Expenditure Approval : Q1:2018
8RFQ Date: Apr/2019
8Release Date: May/2019
8Start Date : Q2:2019
8Completion Date : Q3:2019
Click here for more details.

8Project Name: Greenfield LPG Bottling Plant
8Project Cost: Rs 140 Crore
8Project Description: An owner plans to set up an LPG Bottling Plant by installing mounded storage vessels and has run into a slight delay in the selection of PMC contractor has taken place due to land acquisition.
8Project Event: RFQ for Project Management Consultant is expected by May 2018 instead of March 2018.
8Expenditure Approval : Q3:2017
8RFQ Date: May/2018
8Release Date: Jun/2018
8Start Date : Q2:2018
8Completion Date : Q2:2020
Click here for more details.