2.5 MMTPA LNG terminal: RFQ for an EPCC contractor is expected by August 2018
Mar 21: 8Project Name: 2.5 MMTPA LNG Terminal Project 8Project Cost: Rs 2500 Crore 8Project Description: An owner is planning a 2.5 MMTPA plant 8Project Event: RFQ for an EPCC contractor is expected by August 2018. 8Expenditure Approval : Q3:2016 8RFQ Date: Aug/2018 8Release Date: Sep/2018 8Start Date : Q1:2019 8Completion Date : Q4:2020 Get key contacts and multiple parameter project data with us Click here for more details.